Plant Construction Milestones:



July 1997
Leverkusen site investment program
Company´s and employee´s representatives agree on an investment program for Bayer´s Leverkusen site; Therban ® facility becomes first project within this program.

Plant Milestones

September 1998
Corner-stone ceremony for the Therban ® plant in Leverkusen.
March 2000
Installation of hydrogenation reactor in the final construction phase.
April 2000
Setting free the open-air part.
September 2000
Commissioning the process control.